Building - Alterations/Additions/Repairs of Structures in All Use Groups
|
$0.20 per sq. ft.
Minimum fee $90.00
|
Building - Commercial Plan Review
|
$0.04 up to 5,000 sq. ft PLUS $0.03 per
sq. ft. over 5,000. Minimum fee $15
|
Building - Commercial Swimming Pool
|
$360.00
|
Building - Commercial Temporary Certificate of Occupancy (Each 30 Days)
|
$150
|
Building - Elevators, Escalators and Lifts
|
$285
|
Building - Mobile/Prefabricated Homes
|
$55
|
Building - New Commercial (including additions)
|
$0.24 up to 5,000 sq. ft PLUS $0.17 per
sq. ft. over 5,000. Minimum fee $90.00
|
Building - New SF Residential (less than 1,500 sq. ft.)
|
$500
|
Building - New SF Residential (1,501 - 2,500 sq. ft.)
|
$1,000
|
Building - New SF Residential (2,501 - 3,500 sq. ft.)
|
$1,500
|
Building - New SF Residential (3,501 - 4,500 sq. ft.)
|
$2,000
|
Building - New SF Residential (4,501 - 7,500 sq. ft.)
|
$3,000
|
Building - New SF Residential (greater than 7,500 sq. ft.)
|
$4,000
|
Building - Paint Spraying Booths
|
$30
|
Building - Residential Accessory Structure (attached garages, detached garages, sheds, decks, and porches 10 sq. ft. or larger)
|
$0.18 per square foot, calculated on gross finished square footage.
The minimum fee is $35
|
Building - Residential Plan Review
|
$0.05 per sq. ft. Minimum fee $10
|
Building - Tents and Residential Swimming Pools, Hot Tubs, or Spas
|
$60
|
Building - Demolition Permit
|
$110
|
Electric - Alarm Systems
|
$0.04 per sq. ft. Minimum fee $90
|
Electric - Commercial Plan Review
|
$0.01 per sq. ft. Minimum fee $15.
|
Electric - Early Service
|
$70
|
Electric - Residential Plan Review
|
$0.05 per sq. ft.
Minimum fee $10.00
|
Electric - Signs
|
$55
|
Electric - Mobile/Prefabricated Homes, Fuel Dispensing Pumps, Residential Accessory Structures, Service Change, Swimming Pool, Hot Tub, or Spa (bonding and wiring separate fees)
|
$35
|
Electric - Temporary Service
|
$110
|
Electric- Additions/Alterations/Repairs
|
$0.04 per sq. ft. Minimum fee $90.
|
Mechanical - Above Ground Tanks
|
$120
|
Mechanical - Additions/Alterations/Repairs
|
$0.04 per sq. ft. Minimum fee $90
|
Mechanical - Commercial Plan Review
|
$0.01 per sq. ft. Minimum fee $15.
|
Mechanical - Furnace/Woodstove/Gas Log System
|
$75
|
Mechanical - Gas/Oil Lines
|
$40
|
Mechanical - Range Hoods
|
$30
|
Mechanical - Hood Suppression Systems, Mobile/Prefabricated Homes
|
$35
|
Mechanical - New Commercial (including additions to existing)
|
$0.04 per sq. ft. Minimum fee $90.
|
Mechanical - Residential Plan Review
|
$0.05 per sq. ft.
Minimum fee $10.00
|
Mechanical - Underground Tanks
|
$200
|
Other - Addition or Change in Contractor After Permit Is Issued
|
$35
|
Other - Administrative Fee for Working Without A Permit
|
$250
|
Other - Change of Building Occupancy Classification
|
$175
|
Other - Code Modification Request (No Refund Allowed)
|
$250
|
Other - Elevator Certificate
|
$100 per elevator
|
Other - Group Home/Daycare/Adult Care Form, With No Inspection
|
$75
|
Other - Permit Extension Request
|
$75
|
Other - Permits, and Plan Amendments
|
$35
|
Plumbing - Additions/Alteration/Repairs
|
$10.00 per fixture Minimum fee $90.
|
Plumbing - Commercial Plan Review
|
$1.80 per fixture; $15 minimum
|
Plumbing - Mobile/Prefabricated Homes
|
$35
|
Plumbing - Commercial (including additions)
|
$10.00 per fixture Minimum fee $90.
|
Plumbing - Residential Accessory Structures
|
$35
|
Plumbing - Residential Plan Review
|
$0.05 per sq. ft. Minimum fee $10.
|
Plumbing - Sewer Laterals (unless the lines are included as part of a permit)
|
$30
|
Plumbing - Water Lines (unless the lines are included as part of a permit)
|
$30
|
Plumbing- Fire Suppression Systems (Sprinkler)
|
$0.95 each head.
Minimum fee $90. Plus, plan review fee $0.02 per sq. ft.
Minimum fee $75.00
|
Inspections - Building (Regular Re-inspections) for each inspection performed after the second inspection of such work.
|
$100
|
Inspections - Building Special Inspections (Unique structures such as bridges and towers, determined by Building Official)
|
$100 per hour
|
Zoning - Inspection (each, preliminary or final)
|
$25
|
Bond Agreement with Surety - Establish, Amend, Replace, Reduce, or Release a Bond
|
$285
|
Easement plat required with site plan or plat amendment
|
$235
|
Easements - Plat(S) With A Deed
|
$900
|
Easements - Plat(S) Without A Deed
|
$580
|
Required Notice – Per notice
|
$235 base fee (at time of application) plus the actual cost of first-class postage and advertisement, once determined.
|
Streets - Authorization for One Or More Private Streets Within a Subdivision
|
$790
|
Private Road Plans
|
$475
|
Public Road Plans
|
$295
|
Streets - Waiver or Variation to Requirements
|
$640
|
Subdivision - 1 or more Special Lots, Boundary Line Adjustment
|
$235
|
Subdivision - Additional Fee for Dam Break Inundation Zones
|
1% of total amount of payment required or
$1,000, whichever is less
|
Subdivision - Extension of Plat Approval
|
$140
|
Subdivision - 2 Lots and Family Subdivision
|
$815
|
Preliminary or Final Subdivision (each) - 3 or more lots
|
$1,300
|
Subdivision - Vacation of A Plat or Part Thereof
|
$285
|
Subdivision - Variation or Exception
|
$980
|
Virginia Erosion and Stormwater Management Program (VESMP) exempt from water quantity and water quality technical criteria – Disturbed area less than one acre
|
Plan review and land disturbance permit or each amendment
|
$240
|
Annual Maintenance
|
$230
|
VESMP exempt from water quantity and water quality technical criteria Disturbed area one acre up to 5 acres
|
Plan review and land disturbance permit or each amendment
|
$565
|
Annual Maintenance
|
$340
|
Single Family (SF) – Land disturbing activity pertaining to a sole single family detached dwelling (including within a common plan of development) with less than 5 acres of land disturbance
|
Plan review, land disturbance permit, and first year annual maintenance or each amendment
|
$235
|
Annual Maintenance, starting with the second year
|
$235
|
VESMP – Small construction activity or land clearing that is less than 10,000 sf within a common plan of development or is equal to or greater than 10,000 sf and less than 1 acre
|
Plan Review and Land Disturbance Permit
|
$235
|
Transfer or Modification
|
$120
|
Annual Maintenance
|
$160
|
VESMP – Small construction activity or land clearing that is equal to or greater than 1 acre and less than 5 acres
|
Plan Review and Land Disturbance Permit
|
$2,205
|
Transfer or Modification
|
$225
|
Annual Maintenance
|
$1,530
|
VESMP – Large construction activity or land clearing that is equal to or greater than 5 acres and less than 10 acres
|
Plan Review and Land Disturbance Permit
|
$2,775
|
Transfer or Modification
|
$285
|
Annual Maintenance
|
$1,925
|
VESMP – Large construction activity or land clearing that is equal to or greater than 10 acres and less than 50 acres
|
Plan Review and Land Disturbance Permit
|
$3,675
|
Transfer or Modification
|
$340
|
Annual Maintenance
|
$2,550
|
VESMP – Large construction activity or land clearing that is equal to or greater than 50 acres and less than 100 acres
|
Plan Review and Land Disturbance Permit
|
$4,980
|
Transfer or Modification
|
$510
|
Annual Maintenance
|
$3,460
|
VESMP – Large construction activity or land clearing that is equal to or greater than 100 acres
|
Plan Review and Land Disturbance Permit
|
$7,835
|
Transfer or Modification
|
$795
|
Annual Maintenance
|
$5,440
|
Other Services
|
Amendment to Approved Plan
|
$225 per review
|
Bond Agreement with Surety - Establish, Amend, Replace, Reduce, or Release a Bond
|
$285
|
Construction record drawings review
|
$340
|
Exception
|
$270 each
|
Re-inspection pertaining to a single-family dwelling
|
$170 for the first and $270 for each subsequent reinspection
|
Re-inspection not pertaining to a single-family dwelling
|
$285 for the first and $385 for each subsequent reinspection
|
Review of mitigation plan pertaining to a land disturbing activity in a stream buffer
|
$170
|
Stream Determination
|
$320
|
Variation
|
$170 each
|
ARB - Minor Board review (Building permits, major amendment)
|
$700
|
ARB - Minor Staff Review of County Wide Certificates of Appropriateness (Fencing, Equipment, Lighting)
|
$265
|
ARB - Major Staff Review of CWCA (Additions to ARB- approved buildings, Building permits (per review), Minor amendments, Personal Wireless Service Facilities, structures 750 ft or more from EC not taller than 5 stories or located behind a structure that fronts the EC, Other CWCA)
|
$540
|
ARB - Major Board review (Conceptual plan; advisory review; preliminary, initial or final site plan)
|
$1,185
|
Entrance Corridor - Resubmittal of Any Sign
|
$65
|
Entrance Corridor - Review of any Sign
|
$130
|
Bond Agreement with Surety - Establish, Amend, Replace, Reduce, or Release a Bond
|
$285
|
BZA - Variance and Special Use Permit
|
$590
|
Floodplain - Floodplain Impact Plan Review or Letter of Map Amendment (LOMA) (topographic plan with floodplain model)
|
$355
|
Floodplain - Letter of Map Change review (topographic plan only)
|
$175
|
Groundwater Assessment - Tier I
|
$60
|
Groundwater Assessment - Tier II
|
$390
|
Groundwater Assessment - Tier III
|
$605
|
Groundwater Assessment - Tier IV
|
$1,300
|
Zoning Determination
|
$220
|
Required Notice (per notice)
|
$235 base fee (at time of application) plus the actual cost of first-class postage and advertisement, once determined
|
Sign Permits – Architectural Review Board not required (Temporary Signs)
|
$30
|
Sign Permits – Architectural Review Board required
|
$140
|
Site Development Plan - Additional Fee for Dam Break Inundation Zones
|
1% of total amount of payment required or
$1,000, whichever is less
|
Site Development Plan - Initial Site Plan, Final Site Plan, Major Amendment and Exception to Drawing Site Plan
|
$1,775
|
Site Development Plan - Letter of Revision
|
$120
|
Site Development Plan - Preapplication Plan and Minor Amendment
|
$590
|
Special Exception
|
$980
|
Tier II PWSF
|
$2,155
|
Site Development Plan - Variation or Exception Under Section 32.3.5
|
$980
|
Special Use Permit Minor – Home occupation, class B and Day care center
|
$1,185
|
Special Use Permit - Farmer's Market
|
$130
|
Special Use Permit – All Other Special Use Permits and SUP Amendment (fee includes application and first resubmittal)
|
$2,365
|
Special Use Permit - Deferral of Scheduled Public Hearing at Applicant’s Request
|
the actual cost of first- class postage and advertisement, as applicable
|
Special Use Permit - Telecommunications, Solar
|
$2,365
|
Special Use Permit - For each Resubmittal after the First
|
$590
|
Zoning Clearance - Home Occupations
|
$30
|
Zoning Clearance - All other uses
|
$60
|
Zoning Clearance - Homestay
|
$120
|
Zoning Clearance - Temporary fundraising activity
|
No Charge
|
Zoning Map Amendment - Amendment Pertaining to Proffers which Do Not Affect Use or Density
|
$505.00 application fee plus $235 notice base fee (at time of application) plus the additional cost of first- class postage and advertisement, once determined.
|
Zoning Map Amendment - Deferral of Scheduled Public Hearing at Applicant’s Request
|
the actual cost of first- class postage and advertisement, as applicable.
|
Zoning Map Amendment – Resubmittal and Reapplication of a withdrawn application
|
$1,480
|
Zoning Map Amendment - (Fee includes initial application and first resubmittal)
|
$2,960
|
Appeal – Board of Building Appeals
|
$350
|
Appeal – Board of Supervisors
|
$350
|
Appeal – Board of Zoning Appeals
|
$350
|
Appeal – County Engineer Determination
|
$350
|
ACSJA - Amend Service Authority Jurisdictional Area
|
$130
|
Agricultural and Forest District – Withdrawal of Local or State District
|
$250
|
Short Term Rental Registry
|
$30
|
Technology Surcharge - Additional Fee charged as a percentage of each fee (Does not apply to required notices in Chapters 14 & Chapter 18, State Permit Issuance Fee,
and Dam Break Inundation Zone)
|
4%
|